Hi Kim
Here are the two last excel costing files - click to download:
BQ Diveschool 3 - with temple tile roof
BQ Diveschool 4 - with cost cuts
Best regards
B
Saturday, May 03, 2003
HI KIM
COST CUTTING ITEMS – DIVE SCHOOL
1. CHANGE ROOF TO GRASS (KEEP SAME DESIGN STYLE)
Maybe we change back to Temple Tiles in 2 or 3 years – I will get price from local people through Seng Chai for grass roof.
2. CHANGE FROM SANDSTONE TO FACE BRICK FOR OUTSIDE WALLS
Maybe we change back to Sandstone in 2 or 3 years. Please tell me what price to use now for labor – we used first cost 210 for materials and 95 for labor.
3. REMOVE THIRD FLOOR SLAB AND REDUCE STRUCTURE COST
We take off third floor concrete slab, and if possible reduce cost for structure. Also change structure to foundations if possible for faster. >>> Remember we wanted to put 2 water tanks in the roof for water supply – not in first pricing!
4. CHEAPER DOWNLIGHTS – OK I can do
5. CHANGE FOOR TILES TO CEMENT IN AREAS
You told me to change to 50 Baht per square meter for cement topping include some green/black/red powder color.
I found some other small mistakes in the architect’s drawings:
Bill